Important magnitudes:
– 400 kV GIS substation with two biphase connected positions, two 30 MVA traction transformers.
– 12 auto-transformation centers (20 kV) feeding auxiliary tunnel installations.
– Laying and connection of 360 km of MV cable with 18/30 kV insulation.
– Associated energy remote control.
– Civil works associated with the facilities.